Saturday, July 23, 2016

Standstill

Norman just whatsapp us today that he does not expect any works to be done the next few days. There is little he can do since none of the major masonry are approved. And because of that, the subsequent carpentry and tiling cannot continue.


We have 4 permits pending and each contain several work items. Without the approvals, none of the flooring can continue. It's frustrating to see good progress come to a standing halt. But well there is nothing we can do but wait.

I'm going to give it a week ... and if things don't move, we are considering paying out new MP a visit. Surely he will try to help new residents moving into this ward? ;-P

Friday, July 22, 2016

Steady Progress

It's been steady and very fast progress so far. Things are coming together and looks good so far. But we may be nearing the end of what we can do as far as the permits allow. We have a few pending and I'm hoping they would be approved as we can keep this pace. Below are some of the notable progress.


The marble is turning out beautifully. Even the entrance curb looks a tad more stylish with marble.


They have completed the living and dining area, except for the skirting which will come much later.


The kitchen area are also completed as much as possible. I think they need to work on the carpentry and piping before further tiling can continue. Also the pending levelling of the flooring is holding up the bottom tiling.


The master toilet tiles are also up. Hmm do you find the right ones a different shade from the ones on the left of the picture? Did they send the wrong shade? I'll have to check this out clearly tomorrow.

Thursday, July 21, 2016

Tiling Begins

As the marble progresses, Norman has his tiling team work on the kitchen and bathroom masonry works. The common bathroom door shift has been approved so most of the tiling works can begin for that area. The permit for the master bathroom wall hacking is still pending so we'll gonna have to wait to start there.


Pretty surprised with the rate of progress. If we keep at this pace, we might just be able to move before the end of August. Of course that's assuming we can find a good date to move. Nonetheless happy to see the place coming into shape.




Wednesday, July 20, 2016

No Go On Kitchen Exhaust

Since we have had the experience of living in 303, we know exactly what are common inconveniences and areas which we like to improve.

One of the key renovation detail we wanted was an exhaust fan for the kitchen, similar to the ones we have for our bathrooms. We cook a lot and sometimes the kitchen would be a chamber of grey smoke. It's especially bad when we try to make chilli or curry.


Atlas, it wasn't to be. We received a flat no from HDB, "Exhaust fan: Only allowed at bathroom windows, kitchen NOT allowed." There was no reason attached as to why the decision was made as such.

Norman tried to offer that HDB may be afraid that the exhaust fan will blow out the fumes out of the kitchen window and stain the upstairs neighbour's clothes. Hmmm even without a exhaust fan, isn't smoke already traveling out a kitchen window? It's called proper ventilation ... HDB should come by my block on the weekends when my neighbours cook up a feast. The whole place is a marriage of many different smells and aroma. I never hear anyone complaining about it.

From a technical perspective I don't see any concern. The area is where the clothes hanger are so there shouldn't be any concerns of the exhaust fan cover protruding out and obstructing scaffolding for exterior wall painting. I really wonder if I should appeal, or at least follow-up with the officer to understand why it was rejected.

The Marble Arrives!

The marble is arriving today. Meimei was so excited that she came along on the daily lunch trip to 405. I'm trying to make it a point to go there everyday where possible.


The first sight that greeted us as we drove into the carpark was that of the supplier's truck. Meimei skilfully took this picture while I drove in.


We went up to find that the marbles are all uplifted and laid across the room in stacks. The dry lay plan has been sticked onto the living room wall for reference. I'm glad I finally met Alex in person. He seems like a trustworthy fellow.


His team were in the midst of calibrating the layout. They had drawn thin line across the cement screed to mark out the tile position. We left shortly after as we didn't want to get in their way.


While we were at work, Papa came over to 405 to check on the progress. He even video-ed how the tilers were laying the marble slabs. They would throw glue on the area and lay the tile down. Then one person would step on and push the tile from left to right using his body weight. And while doing so, try to steer the marble into alignment and close the gap with the other pieces. It was interesting to see how it is actually done.


We came again in the evening, anxious to see how it is turning out. I'm amazed at their speed of work. Already most of the easier pieces are done. I'm guessing the next couple of days would be on the side pieces where they would need to cut into shape and size. I can't wait for all of the marble flooring to be done!!

Monday, July 18, 2016

Screeding The Living Area

I decided to pop by during lunch to see if there was any progress. Alex and his marble team were working on Saturday morning so I wanted to see the works.


I was greeted with this the moment I stepped out of the lift. Wow, they are fast! They were supposed to do the waterproofing first and then lay the cement screed. Looks like all these were only done this morning.


I opened the door to find the rest of the living room in wet cement. Notice the footprint on the bottom of the picture? That's another group of workers, the tiling team working on the wall screeding and minor touchups for the kitchen and bathroom.


Since I couldn't enter the flat, I came by again later at night. The packs of prepack cement are now gone from the living room and the rest of the dining and balcony area are done too. Looks like everything is going at bullet pace.

Meimei's Gift Blitz

Meimei is devising a gift blitz to win over Emily. She's pulling out all her cards with this bright red tricycle.


Saturday, July 16, 2016

Marble Hunt 之 Mar-nificent Vanilla Cream

Today's one of the highlights of the renovation so far, the marble dry-lay. This is the first time we will be seeing the marbles to be laid on our living, dining and balcony area. It was pretty much a leap of faith when we confirm the Vanilla Cream. We were just hoping it will turn out as beautiful as we have dreamed it will be.


We were not disappointed. It was white-ish cream with a greyish undertone. Exactly what we wanted for the flooring to suit our white / beige / greyish colour scheme. And it looks stunning in 90x90 cm cut. Perfect.


Because these tiles do not have lines, the dry-lay was simple. We just had to make sure the shades were consistent and flowing. Also to check that there were no unsightly blemishes in the tiles at the walkways. Meimei has an eye for colours and details so she was directing the workers to move slabs around. I, for my part, was like a little kid in a new playground, walking around gleefully, examining and "sayanging" the tiles heheheh. Oh I can't wait for them to start the tiling works!

Friday, July 15, 2016

A Major Leak

There are many things you don't see when buying a old flat. Areas of potential issues are usually covered by build-in furniture. Or owners may strategically place cabinets or beds to cover unsightly areas or pop-up tiles. I was mentally prepared that there will be unforeseen things we need to fix. But that said it still bothers me while we have to deal with the situation.



In our case, a bad leaking problem at the master bathroom where the water is sipping down behind build-in wardrobe. I recalled I was very cautious in checking the two bathrooms for leakage ... and still I didn't catch it. It was only when we inspect the unit a week ago with our ID that he spotted a droplet falling from the bathroom entrance beam. We immediately called Julina to schedule an appointment with HDB to review the leak. This is going to be a problem for our renovation.


So this week we hacked everything in the unit and now that the carpentry is gone we can inspect clearly the magnitude of the seepage. It looks like it has been happening for some time. The wall has gone all mouldy and soft.

The HDB officer has come to look at it yesterday and she is commented that the leak is pretty bad. Great that she acknowledged it, but cold comfort for what's to come. She's going to engage her plumber to check the upstairs unit. 

I've done some snooping online and it seems getting the upstairs neighbours to make the repairs is not an easy process. Most don't want to go through the trouble or pay for it ... it doesn't affect them anyways. So we are crossing our fingers that they would be cooperative. We'll know more next week once they have checked them.

Thursday, July 14, 2016

And So It Begins

We officially started the renovation yesterday. The first step was to clear a section of the floor in the living, kitchen and bedroom to figure the depth of the as-is cement screed and how much we can drop in for the floor thickness.


It seems there is a new regulation since we last renovated our existing 303. The thickness of the cement base plus the tiling cannot be more than 5cm. We were also drilling in hopes that the flooring was thicker than expected so we can drop the height to achieve between 255-260cm ceiling height to fix up a ceiling fan in the living room. 



Sadly it wasn't to be ... The reduction in height is only about 2-3cm. As it turns out, the ceiling at 405 was lower than 303! And all these years I was under the impression that the older flats had taller ceiling.



There is huge progress in the hacking works today. A key find is that we can confirm the bedroom laminates were not overlay over original tiles. That means we don't have to redo the cement screed and thereby saving $2.2K from the ID quote. That money can now go to doing up top hung cabinets in the living room.



The whole place was already torn up when I arrive at noon to inspect the progress. They have even hack the new kitchen entrance. Tomorrow's dedicated to hauling the debris out of the unit and uplifting all the pre-pack cement and tiles. The exciting parts are likely to only come next week.

Wednesday, July 13, 2016

Scouting For Toto

I am on leave again, this time for the vaccination appointment at Mandai before my trip to Australia with my reservist unit. I was done with the jabs by 2pm and decided to drop by the Toto showroom at Bukit Timah. I've been trying to find other retailers but it seems W.Atelier looks to be the sole distributor for Toto in Singapore.

Toto products are known to be pricer than your average bathroom wares. Interestingly though you'll see it often at the toilets of all major shopping malls. 

LW642CJ - List Price $405
Meimei wanted the LW642CJ model of wash basin which she has been using in her office washroom. She like that it has a longer depth and is deep so water will not splash onto the clothes. I get that it is good but at $400, it is really steep for a wash basin. And we are likely to be installing this in the common bathroom since we cannot afford the protruding design in the master bathroom.

LW540J - List Price $305
For the master we are likely to go with a fully recessed basin. Although it may seem that this is more economically priced, you have to consider that the faucet for a recessed basin are typically more expensive than a basin mounted one.

LW645JN - List Price $480
If I had my way, I would go for a counter top sink. It looks classier for a master bathroom vanity counter. Meimei veto-ed it immediately when she saw it. The sink wasn't deep enough so its a no-go.

I think I might come by again when we are ready to purchase the bathroom wares. I'm excited to bring Meimei here to check out all the Toto stuff hehehe.

Needle Attack

5 jabs for our country. 2 on the left, 2 on the right and 1 right in the tummy, right beside the belly button.




Finding Baby's Treasures

Emily has a habit of putting her toys into bags. It's like a treasure hunt with unexpected finds in your bags.



Monday, July 11, 2016

16 Months - Picking Up Bad Habits

16 months and she is now picking up bad habits. We have to be more careful in how we act as she may just pick up silly gestures and movements from us. Already she likes to shrug her shoulders and she does it often. Oh and she seems to understand what we are saying, but refuses to mouth proper words. Hopefully she'll start to articulate better next month *cross fingers.

Emptying her cupboards ... everything is a toy!
Queen Amidala headwear?
Pure glee~
Getting stuck in a box
Messy breakfasts are always the most fun~!!
Catching the wind with Mami

Saturday, July 9, 2016

Blum Adventure

Our ID has been chasing us to look through the design we want for the kitchen cabinets. It may look simple from the 3D drawings but the key is making the cabinets useful in line with our lifestyle.

There are many regrets with our existing kitchen cabinets. Sections where it is too deep and we couldn't reach in to grab the bottles of sauces and condiments. A pantry which is on the upper shelf blocked by a breakfast counter. A corner door mechanism that doesn't really work and closes weirdly. Many many examples to fuel our experience and what not to have in the new place.

So it's with this mindset that I insist we make a trip to Blum. I wanted to see what all the hype is about and also see if we can steal some ideas for our kitchen. They have showflat kitchens so that really helps in visualising the different sections of space.


Sauce drawers beside the stove. Meimei list this down as a definite must have. And I have to agree, it's just so convenient. And below that we can put the cooking oil and other miscellaneous cooking accessories.


Multi-tier long drawers for the cutleries and plates. Yes, we are replacing a set of casement doors with this for sure.


Half depth drawers below the sink to keep the washing accessories. Hmm I'm undecided about this one. We would lose some of the space at the deeper end. And imagine the hassle of trying to remove the drawer to make repairs on a leaking sink. I might just opt for a casement door section for the sink.


Another must-have. Very useful to house pots and pans below the stove. The pull out drawer makes it easy to reach them unlike the normal casement where you have to squat down to reach your desired pan.

All in all it was a very fruitful trip. We learned a couple of new ideas for the kitchen. I think the only stumbling block to getting our dream kitchen would be the cost. I'm gonna have to work out how much all these extra Movento runners for drawers are going to set us back on the budget.